Progress Claim Format Malaysia
Last updated: 12 November 2026
Searching for a progress claim format Malaysia teams can reuse? This guide covers what a typical interim claim certificate includes (BQ lines, period, retention, SST, claimed / certified / paid), and how to produce that format from a BuildTrack project — without rebuilding the spreadsheet every claim cycle.
What consultants expect to see
In Malaysia, an interim progress claim is usually a certificate against the project BQ — not a free-form invoice. A clear format typically includes:
- Project name, contract reference, and claim period (dates)
- BQ (and VO) lines with cumulative percentage complete
- This period’s claim amount in MYR, retention held, and SST if applicable
- Running totals: claimed, certified, and paid to date
- Optional evidence photos or an appendix for the site visit
That layout is what QS and client accounts teams certify against. BuildTrack’s claim certificate PDF follows the same structure so you are not rebuilding a spreadsheet each month.
Claimed vs certified vs paid
A solid format keeps three money columns honest. Claimed is what you submitted. Certified is what the client (or consultant) accepted. Paid is what hit the bank. Retention sits beside those totals so net payable for the period is obvious. See Issue Progress Claims for how to raise, certify and record payment on a project job.
Progress claim vs progress report
Do not mix the payment certificate with the monthly works statement. A progress report summarises work done, variations and photos for the consultant. A progress claim bills against the BQ. Both are common on Malaysian projects; they are separate documents.