BuildTrack
PricingSupport
011-2057-8260Log in
Accessible anywhereUpdate progress, photos and claims from your phone.
Get paid, your wayOne payment link: FPX, DuitNow QR and card.
See the full platformFrom leads to MYR billing in one place.
Plans that scale with youFrom solo trades to multi-site builders.

Sales

  • Lead management
  • Quotation software
  • Contractor CRM

Delivery

  • Job & site tracking
  • Crew scheduling & Live
  • Daily site reports
  • Construction project management
  • Robin

Finance

  • Payments & collections
  • Progress claims
  • Job costing & profitability
  • Variation orders & SST

People

  • Contractor payroll & commissions
  • Time & attendance tracking
  • Labour cost tracking

Firm Type

  • Main Con
  • Sub Con
  • Owner
  • Designer

Issue Progress Claims

Last updated: 15 October 2026

On construction work you rarely bill everything at the end, you claim progressively as each stage completes. A Progress Claim is a schedule-of-values certificate against the project BQ (and variation orders), with optional evidence photos. BuildTrack keeps a running total of what has been claimed, certified and paid so you never over-claim or lose track of what a client owes.

Progress Claim prerequisites

Progress claims are for project jobs only. You need a contract sum and a saved BQ. If you started from a quotation, that value carries across when you convert the quotation to a job. On Contract → Bill of Quantities, tick BQ items, or open one, then click the programme task that delivers them. Weights split evenly. Type a % on the row to change one. Build the programme under Programme → Schedule first if there are no tasks yet. See Run a project.

Raise a Progress Claim

  1. 1

    Create a draft on the Contract tab

    Open the project → Contract → Progress claims. New progress claim creates a draft straight away. A description and claim period are optional. Lines come from the BQ (using linked-task suggested %) and from approved variation orders.

  2. 2

    Review percentages and evidence

    Edit cumulative % per line, or use Apply suggested. Attach site photos as claim evidence, they appear on the certificate PDF appendix.

  3. 3

    Submit and share with the client

    Submit moves the claim to submitted and freezes the BQ. Open the claim PDF and/or send a WhatsApp message with the claim summary and PDF link.

  4. 4

    Certify and record payment

    Record the certified amount when the client certifies. Log the payment received, then apply it across the certified claims it covers. Retention and SST follow the project contract settings.

A Progress Claim is a payment certificate against the contract, not the same document as a sales invoice. BuildTrack tracks claimed, certified and paid separately so you do not over-claim the contract sum.

Track Progress Claim amounts

The claims register and project summary show what has been claimed, certified and paid in MYR, plus retention held. Use Share / Chase on WhatsApp when amounts are outstanding. The monthly statement you send the consultant is a separate document. See Issue a progress report.

Common questions

BuildTrack

Construction management software for Malaysian teams, from programme through to MYR billing.

Product

  • Products
  • Pricing

Firm types

  • Main Con
  • Sub Con
  • Owner
  • Designer

Company

  • Careers

Get started

  • Log in
  • Get demo

Support

  • Help Centre
  • Contact us
  • 011-2057-8260
  • hello@buildtrack.com.my

© 2026 BuildTrack. All rights reserved.

Terms of ServicePrivacy PolicyDPASitemap